Requirement to increase reliability and operability of new and existing equipment, increase energy efficiency and improve safety functions.
Increase reliability of hazardous fluid detection and metering. Replacement / introduction of over of 15 new vessels and further equipment. Improved reliability, operability and maintainability of new and existing equipment. Steam system modifications to increase energy efficiency. New automated start up sequence. Adequate independence between SIL interlocks. Venting Safety improvements.
CIE completed the EC&I, piping, civil and structural design as well as construction management and pre-commissioning.
Increased reliability, quality, capacity and efficiency for the plant, reduction in operating costs.
Control system no longer supported, significant cost required to maintain support, hardware became obsolete
Upgraded legacy DCS including HMIs, controllers, I/O, batch recipes exported and re-integrated. Site system upgraded to latest version of Delta V.
>800 I/O migrated, use of field mounted solution to minimise down time. CIE responsible for E&I design and pre-commissioning
20 new field distribution and CHARMS cabinets installed
Installed cut over and commissioned within 3 weeks.
Delivered on time, more streamlined, more visibility and control for the site
Provide verification of installed equipment, instrumentation & pipework to ensure compliance with process design & relevant design codes.
Verify installation of 3off 20tph 25barg boilers, 330 isos, 11 P&IDs, 212 E&I items, management of over 1,400 items on the punch list and action close out, handover to client
Client is now reliably generating their own steam, rather than relying on external utilities supplier.